UIG Harbour Redevelopment
Description.
FMD was Subcontracted to dredge approximately 27,000m3 of seabed material into a split hopper barge and disposal at the nearby approved disposal site.
A busy site with various interactions with other marine construction vessels.
- Tara Marie Dredger with EX1200 triple boom Grizzly Excavator
- Boss Tug
- 335m3 hopper barge

CLIENT
The Highland Council
PRINCIPAL CONTRACTOR
RJ McLeod Limited
LOCATION
Ullapool, Northern Scotland
PRINCIPAL SCOPE OF WORKS
Dredge approximately 27,000m3 of seabed material into a split hopper barge and disposal at the nearby approved disposal site.
DURATION
9 weeks (Jan – March 23)
COMPLEXITY
Challenging