Description. 

FMD was Subcontracted to dredge approximately 27,000m3 of seabed material into a split hopper barge and disposal at the nearby approved disposal site. 

A busy site with various interactions with other marine construction vessels. 

 

  • Tara Marie Dredger with EX1200 triple boom Grizzly Excavator
  • Boss Tug
  • 335m3 hopper barge 
UIG Harbour Redevelopment Dredging Aerial View

CLIENT
The Highland Council

PRINCIPAL CONTRACTOR
RJ McLeod Limited

LOCATION
Ullapool, Northern Scotland

PRINCIPAL SCOPE OF WORKS
Dredge approximately 27,000m3 of seabed material into a split hopper barge and disposal at the nearby approved disposal site.

DURATION
9 weeks (Jan – March 23)

COMPLEXITY
Challenging