Multiflex logo

Location

Colab Centre,
Port Road,
Letterkenny,
Co. Donegal

Office hours

Mon – Fri
8:00 – 5:00

Call us Today

353872221953

Multiflex logo

Call us Today

087 222 1953

Stradbally 225OD HDPE Outfall, Stradbally, Co Waterford

<iframe src="https://www.google.com/maps/embed?pb=!1m18!1m12!1m3!1d9601.012978869427!2d-7.158226359703164!3d53.01581038743956!2m3!1f0!2f0!3f0!3m2!1i1024!2i768!4f13.1!3m3!1m2!1s0x485d72881b2435cd%3A0xa00c7a99731d0a0!2sStradbally%2C+Co.+Laois%2C+Ireland!5e0!3m2!1sen!2sus!4v1513183717984" width="100%" height="250" frameborder="0" style="border:0" allowfullscreen></iframe>

Challenges presented

  • 100M of rock breaking within the outfall trench alignment
  • Outfall location

Sorensen Civil were assigned as principal contractor for the Stradbally Waste Water Treatment Plant. This project and outfall pipeline was part of upgrading the exiting treatment system for the area. Once again Sorensen Civil appointed Foyle & Marine Dredging as the contractor to construct and install the outfall 120M 225OD HDPE outfall pipeline.

The complex location of the proposed outfall provided limited option for the trench to be installed via floating plant methods.
Foyle & Marine executed the trench excavation and rock breaking work via a 45T and 20T Hitachi excavator. A temporary revetment was developed alongside the proposed trench alignment to conduct rock breaking and trench excavation during tidal ranges. The 45T was equipped with a Prolec Pcx dig system for accuracy.

The 120M outfall included 30No anchor block and a single point diffuser was installed over two tides. The marine section was floated off the beach, connected to the shore end and lowered into the pre-dredged trench in a controlled manner. On completed outfall installation, a dive survey was conducted prior to backfilled the pipe with existing material.
The treatment plant was successfully commissioned later that year.

CLIENT
Waterford County Council

PRINCIPAL CONTRACTOR
Sorensen Civil Engineering Contractors

LOCATION
Stradbally, Co Waterford

PRINCIPAL SCOPE OF WORKS
120M of 225OD Outfall Trench Excavation & Placement

DURATION
4 Weeks April 2015 – May 2015

DURATION
Average

ROI Head Office

Foyle & Marine Dredging
Glencrow Business Park
Moville
Co. Donegal

Stephen Mc Cormick Mobile: +353 87 222 1953