Nigg South Quay Development, Nigg Scotland

<iframe src="https://www.google.com/maps/embed?pb=!1m18!1m12!1m3!1d8660.931730192657!2d-2.0626755571980833!3d57.133079640009356!2m3!1f0!2f0!3f0!3m2!1i1024!2i768!4f13.1!3m3!1m2!1s0x48840eff72ecf9c9%3A0x4a486079a29d6d41!2sNigg+Bay!5e0!3m2!1sen!2sus!4v1513183302340" width="100%" height="250" frameborder="0" style="border:0" allowfullscreen></iframe>

Challenge presented on this project.

  • Density & depth  of existing material between –10 to -12CD

Mc Laughlin & Harvey required an excavator with long reach capabilities to dredge and side cast hard bolder clay material at a depth of -12CD from the steel sheet wall into the path of a trailer suction dredger.

Foyle & Marine’s EX1200 has an outreach of 30M and a dredge depth of 18M. The client required these dredge capabilities to reduce the marine material around the existing piles to -16.5 to allow divers to cut the piles at -15CD. The excavator also completed a sweep of the dredge area removing any isolated hire areas and ensure the -12CD design level was achieved throughout.

Foyle & Marine’s 45T long reach excavator was also positioned along the new quay wall remove material built up within the steel sheet piles. This material was side casted into the path of a mult-cat plough for removal.

CLIENT
Globle Energy Group

PRINCIPAL CONTRACTOR
Mc Laughlin & Harvey

LOCATION
Nigg, Scotland

PRINCIPAL SCOPE OF WORKS
Dredging of hard material and side casting for TSD -12CD
Exposing existing piles to be reduced below -16.5CD

DURATION
15 Weeks January 2015 – April 2015

COMPLEXITY
Average