Clyde Waterfront Renfrew Riverside
Description.
Dredging approximately 25,000m3 of seabed material to -10mCD, within the works area, and disposal at the project-approved disposal ground at Cloch Point.
These dredging works were on the project critical path as they needed to be completed before the 29th of February 2024, as environmental licencing conditions did not permit dredging activities from 1st March 2024 for several months.
- Dinopotes Backhoe Dredger
- Willpower Tugboat
- 450m3 hopper barge

CLIENT
Renfrewshire Council/Glasgow City Council
PRINCIPAL CONTRACTOR
John Graham Construction Limited
LOCATION
Clydebank Glasgow
PRINCIPAL SCOPE OF WORKS
Dredging approximately 25,000m3 of seabed material to -10mCD.Disposal.
DURATION
6 weeks (Jan/Feb 2024)
COMPLEXITY
Challenging