Ardmore Outfall
Challenges presented
- Trench excavation in open waters
- 250M of Rock breaking within the outfall trench alignment
Sorensen Civil was assigned as principal contractor for the Ardmore Waste Water Treatment Plant. This project and outfall pipeline was imperative for the Ardmore community in order to maintain the local beaches’ blue flag status.
Sorensen appointed Foyle & Marine Dredging as the contractor to construct and install the outfall 715M long outfall pipeline.
Foyle & Marine constructed and installed the 160M of the shore section first, thus creating the ideal location for the shore marine connection within the tidal range.
The marine section was dredged by the Backhoe dredger Aoibheann along with a transfer barge to carry the required rock breaking equipment. For complete dredging and rock breaking accuracy, the outfall alignment, trench information was uploaded to the Spud leg dredger Aoibheanne’s Prolec Pcx dredge system prior to commencement.
The 550M marine section including 150No of anchor block was constructed along the shoreline in two sections as the marine trench was being excavated. Over two tides the marine sections were floated off the beach, connected to the shore section and lowered into the pre-dredged trench in a controlled manner. On completed installation, the diffuser was installed and scour protection placed around the diffuser. The completed pipe alignment underwent a detailed dive survey prior to being backfilled with existing material.
The treatment plant was successfully commissioned later that year.

CLIENT
Waterford County Council
PRINCIPAL CONTRACTOR
Sorensen Civil Engineering Contractors
LOCATION
Ardmore, Co Waterford
PRINCIPAL SCOPE OF WORKS
715M of 315Outfall Trench Excavation & Placement
DURATION
12 Weeks March 2015 – May 2015
COMPLEXITY
Average – Difficult
ROI Head Office
Foyle & Marine Dredging
Glencrow Business Park
Moville
Co. Donegal
Stephen Mc Cormick Mobile: +353 87 222 1953